CEBU BUS RAPID TRANSIT PROJECT UPDATE ( FINALLY ITATAYO NA)

j

by Kivi

}

08.13.2022



CEBU BUS RAPID TRANSIT PROJECT UPDATE

THE construction of Package 1 of the Cebu Bus Rapid Transit (BRT) project is expected to begin within the first 100 days of President Ferdinand Marcos Jr.’s administration.

The Department of Transportation (DOTr) is currently reviewing the documents of three bidders for the project, 

Package 1 includes Osmeña Blvd., from the Cebu Provincial Capitol and going right to the Cebu South Bus Terminal (CSBT) along N. Bacalso Ave.

Engineer Roberto Varquez, BRT focal person for Cebu City, said they are waiting for the report from the special bids and awards committee of DOTr.

According to Varquez, DOTr Secretary Jaime Bautista wanted the project to be awarded to the winning bidder within the first 100 days of the administration of Marcos Jr.
The bidding for Package 1 of the project, which costs about P1 billion, started in May 2022.

Five interested contractors joined the bidding, but two were declared unqualified based on their documents.

Once the notice to proceed will be given to the winning bidder, civil works for the project will immediately be implemented, Varquez said.

This will include the construction of four bus stations that will be located in the Cebu South Bus Terminal, Cebu Normal University, Fuente Osmeña and the Cebu Provincial Capitol.

Last June, a total of 228 trees were earth-balled along the route of Package 1 of the project.

BRT project officials said the earth-balling of trees located in the center island was necessary since the dedicated lanes for the buses will be placed there.

The project implementation unit (PIU) of the Cebu BRT has also started its initial preparatory activities for the project’s Package 2.

Package 2 of the BRT is composed of the routes from the South Road Properties (SRP) to the CSBT and another route from Capitol to the Cebu IT Park in Barangay Lahug.

Package 3 will include the routes from Talisay City to Barangay Mambaling, Talisay City to SRP, and Cebu IT Park to Barangay Talamban.

The Cebu BRT project is funded by the French government through Agence Française de Développement (Euro 50.89 million); the International Bank for Reconstruction and Development ($116 million), the lending arm of the World Bank Group; the Clean Technology Fund ($25 million) administered by the World Bank; and counterpart financing from the Government of the Philippines (US$30 million), according to a World Bank report on the project.

#cebubusrapidtransitproject
#cebubusrapidtransitupdate
#buildbettermore

DONT FORGET TO LIKE SHARE COMMENT AND SUBSCRIBE…
HIT THE NOTIFICATION BELL ? FOR MORE UPDATES

MUSIC
YOUTUBE AUDIO LIBRARY

THANK YOU FOR WATCHING!!

HIGHER RANKINGS MORE TRAFFIC

source

Kiviac.com is reader-supported. When you buy through links on our site, we may earn an affiliate commission.

Featured Articles

FOLLOW US

Comments

0 Comments

Related Posts